Global Timeline

All milestones across 8 factories — past and projected.

CONSTRUCTION PROGRESS BY YEAR

🇺🇸 TERAFAB2%
20202026
🇺🇸 Gigafactory Texas78%
20202026
🇺🇸 Gigafactory Nevada65%
20202026
🇨🇳 Gigafactory Shanghai95%
20202026
NOW — APRIL 2026
🇺🇸 Fremont Factoryoperational
2010-05

Tesla acquires NUMMI plant

🇺🇸 Fremont Factoryoperational
2012-06

First Model S delivered

🇺🇸 Gigafactory Nevadaexpanding
2014-06

Groundbreaking

🇺🇸 Gigafactory Nevadaexpanding
2016-07

Grand opening

🇺🇸 Gigafactory Nevadaexpanding
2017-01

2170 cell production

🇺🇸 Fremont Factoryoperational
2017-07

Model 3 production begins

🇺🇸 Gigafactory New Yorkoperational
2017-08

Production began

🇨🇳 Gigafactory Shanghaioperational
2019-01

Groundbreaking

🇺🇸 Gigafactory New Yorkoperational
2019-10

Solar Roof v3

🇨🇳 Gigafactory Shanghaioperational
2019-12

First deliveries

🇩🇪 Gigafactory Berlinoperational
2020-01

Construction began

🇺🇸 Fremont Factoryoperational
2020-01

Model Y production

🇺🇸 Gigafactory Texasexpanding
2020-07

Site clearing began

🇺🇸 Gigafactory Texasexpanding
2021-04

Main structure complete

🇨🇳 Gigafactory Shanghaioperational
2021-10

Export hub established

🇩🇪 Gigafactory Berlinoperational
2022-03

First deliveries

🇺🇸 Gigafactory Texasexpanding
2022-04

First deliveries (Model Y)

🇺🇸 Gigafactory Nevadaexpanding
2023-01

$3.6B expansion announced

🇲🇽 Gigafactory Mexicoconstruction
2023-03

Location announced

🇺🇸 Gigafactory New Yorkoperational
2023-05

Megapack components

🇺🇸 Gigafactory Texasexpanding
2023-11

Cybertruck production start

🇩🇪 Gigafactory Berlinoperational
2023-11

5K/week milestone

🇩🇪 Gigafactory Berlinoperational
2024-03

Arson attack / recovery

🇨🇳 Gigafactory Shanghaioperational
2024-05

Megafactory ground broken

🇲🇽 Gigafactory Mexicoconstruction
2024-06

Permits approved

🇺🇸 Fremont Factoryoperational
2024-10

Refreshed Model 3 US prod

🇺🇸 Gigafactory Nevadaexpanding
2024-12

Semi production ramp

🇺🇸 Gigafactory Nevadaexpanding
2025-Q3

4680 pilot line operational

🇨🇳 Gigafactory Shanghaioperational
2025-01

Megafactory complete (7mo)

🇲🇽 Gigafactory Mexicoconstruction
2025-03

Site prep & grading

🇺🇸 Gigafactory New Yorkoperational
2025-03

Supercharger V4 prod

🇺🇸 Gigafactory Texasexpanding
2025-06

Cybercab pilot line

🇩🇪 Gigafactory Berlinoperational
2025-06

Expansion approved

🇺🇸 Fremont Factoryoperational
2025-06

Model S/X end of production

🇲🇽 Gigafactory Mexicoconstruction
2025-09

Foundation work begins

🇺🇸 Gigafactory New Yorkoperational
2025-10

Solar Roof v4 line install

🇨🇳 Gigafactory Shanghaioperational
2025-12

Megapack production ramp

🇩🇪 Gigafactory Berlinoperational
2025-12

Phase 2 construction started

🇺🇸 TERAFABconstruction
2026-Q3

Pilot fab site prep begins

🇺🇸 TERAFABconstruction
2026-H2

AI5 small-batch production

🇺🇸 Gigafactory Texasexpanding
2026-H2

Phase 3 expansion complete

🇺🇸 Gigafactory Nevadaexpanding
2026-Q4

4680 cell mass production

🇨🇳 Gigafactory Shanghaioperational
2026-Q2

Refreshed Model Y ramp

🇲🇽 Gigafactory Mexicoconstruction
2026-01

Structural steel phase

🇺🇸 Gigafactory Texasexpanding
2026-03

Massive expansion plans filed

🇺🇸 TERAFABconstruction
2026-03-21

Musk announces Terafab launch

🇺🇸 TERAFABconstruction
2026-04

Site selection & environmental review

🇺🇸 TERAFABconstruction
2027

Volume production target

🇩🇪 Gigafactory Berlinoperational
2027-H1

Phase 2 complete

🇲🇽 Gigafactory Mexicoconstruction
2027-H1

Production start (target)